No power, Rs 102 crore Giri water scheme hangs fire : The Tribune India

Join Whatsapp Channel

HIMACHAL TRIBUNE

No power, Rs 102 crore Giri water scheme hangs fire

No power, Rs 102 crore Giri water scheme hangs fire

0nce functional, the water scheme will serve the Kasauli areas.



Tribune News Service

Ambika Sharma

Solan, June 29

The lack of funds for electricity supply to the ambitious Rs 102 crore Giri water scheme, which would serve the Kasauli area, is delaying the commissioning of the project.

The Jal Shakti Department (JSD), which is executing the scheme, recently provided Rs 1 crore to HP State Electricity Board Limited, while a similar amount was deposited in December 2023 against the requirement of Rs 6.94 crore to ensure power supply.

The Rs 102 crore scheme has been funded by the Jal Jiwan Mission (JJM) and the National Bank for Agriculture Development (NABARD). An amount of Rs 56 crore has been provided by the JJM and Rs 46 crore by NABARD.

The triple-stage scheme would lift water from Giri river in Sirmaur district. As many as 179 habitations of Kasauli Assembly segment, with a population of 45,458, will benefit from the scheme, which will supply 7.5 million litre of water per day.

Superintending Engineer, HP State Electricity Board Limited, Nahan, Darshan Saini said as against an estimate of Rs 6.94 crore for supply of electricity to the Giri water scheme, a sum of Rs 2 crore had been received from the JSD, Solan.

“Three tenders have been floated and key procurement works have been completed, while a major work to augment 33-KV substation at Gaura will commence after the remaining amount is deposited by the JSD,” added Saini.

Villages in Kasauli area faced an acute water shortage this summer with no supply for eight to nine days on the trot. In the absence of any other source for irrigation, villagers are forced to divert this water supply to their cash crops, aggravating the crisis.

Though the Giri scheme was supposed to be commissioned by June 2023, various reasons have been attributed to its delay.

There is a dispute between the Public Works Department (PWD) and some land owners at Sihardi village who are objecting to laying pipes along their land.

“The PWD is demanding manual excavation of the 1,500 metre road stretch from Garkhal though the entire amount for the damage caused to the road has been deposited with them,” said Bhanu, SDO, JSD, Dharampur. The official said nearly 80 per cent work to lay pipes had been done and the remaining would be completed as soon as these hurdles were overcome.

About The Author

The Tribune News Service brings you the latest news, analysis and insights from the region, India and around the world. Follow the Tribune News Service for a wide-ranging coverage of events as they unfold, with perspective and clarity.

#Kasauli #Solan


Top News

27 die in stampede at 'satsang' in Uttar Pradesh's Hathras

116 dead in stampede at religious congregation in UP's Hathras

The stampede takes place as people head home after a ‘satsan...

Outside Hathras hospital, bodies of stampede victims lay on the floor, loud wails pierce the air

Outside Hathras hospital, bodies of stampede victims lay on the floor, loud wails pierce the air

The heartbreaking scenes unfold outside the district's Sikan...

Our zero tolerance against corruption has received people's support, we have been solely guided by 'India first': PM Modi in Lok Sabha

PM Modi hurls 'balak buddhi' barb at Rahul Gandhi, asserts mandate is for stability, continuity

Was replying to a nearly 18-hour-long discussion on the Moti...

Punjab bypoll: Days after SAD withdrew support to Jalandhar West candidate, Surjit Kaur joins Aam Aadmi Party

‘Was not a party to it’: Hours after joining AAP, Surjit Kaur is back in SAD

Says was tutored by CM Bhagwant Mann to say that she liked A...


Cities

View All