Nathpa project in jeopardy
From S.P.
Sharma
Tribune News Service
SHIMLA, Oct 18 A
question mark has been put on the completion of the
1500-MW Nathpa Jhakri power project with the World bank
deciding to midway suspends its $ 437 million loan for
the Asia's largest underground hydroelectric project.
The decision of the World
Bank has created panic as the project, near here, has
remained in rough waters ever since work on it began in
1989.
The World Bank, which has
made a commitment for the loan in 1989, has decided to
suspend it because of the continuous delay and
alterations in the height of the dam.
The issue will be
considered by the Public Investment Board (PIB) at its
meeting on October 21. The Nathpa Jhakri Power
Corporation (NJPC) has moved the PIB for revision of the
project cost to Rs 7,217 crore from the initial estimates
of Rs 4,338 crore.
Sources said that the NJPC
had so far spent $ 309 million on the project out of the
World Bank loan. An amount of $ 128 million was
unutilised when the decision to suspend the loan came.
The loan was to be spent by December next. The cost of
the project had escalated several times due to delays in
its completion.
The project was initially
slated to be commissioned this year. However, the target
now has been fixed for the year 2001.
The project sources said
the loan might have to be raised from commercial banks in
case the World Bank did not review its decision.
The project is being
constructed on an equity participation of 75:25 between
the Centre and the Himachal Pradesh Government. Arrears
amounting Rs 75 crore are already to be cleared by
Himachal Pradesh on this account.
Another possibility to
overcome the crisis was to increase the equity
participation of both executing governments. However,
this might not be possible because of financial crunch
facing the state.
Although the World Bank
had from time to time appreciated the progress of the
project, yet it was not prepared to enhance the period of
the loan.
The project has also
suffered because of the ongoing tussle between the
employees of the NJPC and the HPSEB over the working
conditions.
Initially, the project
management was operating from Delhi, but the headquarters
of the NJPC had to be shifted here following a strong
protest by the state government.
|